PROJECT AUTHORIZATION PACKET ID: N/A
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
      67808 22
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER


DPR 0033(002)

08-00059
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
MAJOR WIDENING 33.0 MI
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
DOH DOH DOH
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
DOH/CONTRACT DOH
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL FHWA STATE DOH LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
8-59.2 D 1200 FD52 2012 2012 Q920 $305,018.00
CURRENT FUNDING REQUEST TOTAL: $305,018.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $26,470,646.00
UTILITIES $4,787,000.00
R/W $26,110,000.00
CONSTRUCTION $60,915,888.00
NON-HIGHWAYS $0.00
  Total: $118,283,534.00
REMARKS: THIS MODIFICATION PROVIDES $305,018 OF ADDITIONAL FEDERAL HPP (Q920) FUNDS FOR THE DESIGN PHASE TO COVER A DESIGN CONTRACT MODIFICATION. SAC
 
Project Approval Recommended By:
KFD   7/10/2012
Signed and Approved by:
MH   7/12/2012
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
08-00059.20 PULASKI


8 SOMERSET NORTHERN BYPASS KY 461 33.0 MI CONSTRUCT A SECTION OF I-66 FROM THE CUMBERLAND PARKWAY 3MI WEST OF US 27 NORTH AND EAST TO I-75 AT LONDON.